ANALISIS KINERJA PROYEK SUTT 150 kV TAYAN - SANDAI TERHADAP ASPEK BIAYA DAN WAKTU DENGAN METODE EARNED VALUE
Elektrika Borneo · 2026
DOI: 10.35334/eb.v12i1.7191 ↗Kurz gefasst
Fachartikel in der Zeitschrift Elektrika Borneo, 2026. Verfasst von Sahat Josua Siahaan und 1 weiteren Autor:innen. Die Arbeit wurde bisher 1-mal zitiert (Crossref).
Abstract (Originalsprache)
In a construction project, the key indicators of success are cost, quality, and time performance. To achieve these targets, proper planning, scheduling, and execution control are essential. The Earned Value concept is one of the integrated control methods used to manage both project cost and schedule effectively. This method is applied to analyze project performance and to forecast project completion by providing performance information at a specific reporting period and generating estimates for the total cost and time required to complete the entire project. This final project presents an analysis using the Earned Value Concept to evaluate the contractor's performance, as well as the cost and time aspects of the 150 kV Tayan – Sandai transmission line construction project. The project experienced delays caused by factors related to manpower, methods, materials, and the environment.
Zitieren
APA
Siahaan, S. J., & Adi, T. W. (2026). ANALISIS KINERJA PROYEK SUTT 150 kV TAYAN - SANDAI TERHADAP ASPEK BIAYA DAN WAKTU DENGAN METODE EARNED VALUE. Elektrika Borneo. https://doi.org/10.35334/eb.v12i1.7191
Vancouver
Siahaan SJ, Adi TW. ANALISIS KINERJA PROYEK SUTT 150 kV TAYAN - SANDAI TERHADAP ASPEK BIAYA DAN WAKTU DENGAN METODE EARNED VALUE. Elektrika Borneo. 2026. doi:10.35334/eb.v12i1.7191
BibTeX
@article{Siahaan2026,
author = {Siahaan, Sahat Josua and Adi, Tri Wahyu},
title = {ANALISIS KINERJA PROYEK SUTT 150 kV TAYAN - SANDAI TERHADAP ASPEK BIAYA DAN WAKTU DENGAN METODE EARNED VALUE},
journal = {Elektrika Borneo},
year = {2026},
doi = {10.35334/eb.v12i1.7191}
}
EUVIMED