Demand-Oriented Post-Disaster Repair Scheduling for a Power-Grid-Building System

Ziyue Yuan, Duo Li, Xuekai Cen, Zhongnan Ye, Xinyu Yan

Mathematics · 06.08.2026 · 14 (15) · 2855

DOI: 10.3390/math14152855 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Mathematics, online erschienen am 06.08.2026. Verfasst von Ziyue Yuan und 4 weiteren Autor:innen. Die Arbeit nennt 49 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: National Natural Science Foundation of China, School of Traffic and Transportation Engineering at Central South University.

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

Post-disaster repair priorities can change when building demand and available supply recover at different rates. This study models a power-grid-building system, defines demand loss as cumulative unmet demand divided by cumulative demand, and uses a genetic algorithm (GA) with deterministic feasibility rules to select repair task order and repair mode. The two GA searches used the same settings, 20 runs for each objective, and 36,200 schedules evaluated per run. In the baseline case, the lowest demand loss found was 0.3925 for the demand-targeted search and 0.3995 for the supply-targeted search. The demand-targeted result was 1.7464% lower and reduced cumulative unmet demand by 238 kW-day. Across the same 20 random seeds, the demand-targeted search produced lower demand loss in 16 runs and the supply-targeted search produced lower demand loss in four runs. In a separate comparison with different computational effort, the demand-targeted GA result had 20.3% lower demand loss than one deterministic greedy schedule. Additional five-run analyses show that the observed results depend on GA settings, crew availability, repair duration, and demand timing. The findings apply to the tested deterministic case study and support demand-aware repair scheduling when demand and supply recover at different rates.

Förderung

  • National Natural Science Foundation of China
  • School of Traffic and Transportation Engineering at Central South University

Zitieren

APA

Yuan, Z., Li, D., Cen, X., Ye, Z., & Yan, X. (2026). Demand-Oriented Post-Disaster Repair Scheduling for a Power-Grid-Building System. Mathematics, 14(15), 2855. https://doi.org/10.3390/math14152855

Vancouver

Yuan Z, Li D, Cen X, Ye Z, Yan X. Demand-Oriented Post-Disaster Repair Scheduling for a Power-Grid-Building System. Mathematics. 2026;14(15):2855. doi:10.3390/math14152855

BibTeX
@article{Yuan2026,
  author = {Yuan, Ziyue and Li, Duo and Cen, Xuekai and Ye, Zhongnan and Yan, Xinyu},
  title = {Demand-Oriented Post-Disaster Repair Scheduling for a Power-Grid-Building System},
  journal = {Mathematics},
  year = {2026},
  volume = {14},
  number = {15},
  pages = {2855},
  doi = {10.3390/math14152855}
}
Kostenlos starten →