Coordinated Dynamic Line Rating and Transmission Expansion Planning with Reliable Thermal-Capacity Assessment in Critical Transmission Hours
Electronics · 2026-11-14 · 15 (22) · 5299
DOI: 10.3390/electronics15225299 ↗At a glance
Journal article in Electronics, published online on 2026-11-14. Written by Zhongyi Liu and 4 co-authors. 41 references. The full text is freely available (open access, CC BY 4.0). Funded by: State Grid Tianjin Electric Power Company.
Abstract (original language)
Dynamic line rating (DLR) determines the allowable current of overhead lines based on conductor thermal conditions and weather. Its contribution to transmission planning depends on the additional capacity available on constrained lines during critical hours. This paper proposes a coordinated DLR and transmission expansion framework that determines circuit-specific constant thermal-capacity increments that meet the hourly load-shedding limits of a DLR reference plan and quantifies the associated reduction in additional construction expenditure for a common retained portfolio. Critical-hour selection and security feedback support the planning stage. Restricted optimization and feasible preventive/corrective dispatches certify the thermal and investment bounds under a common DC operating model. On the synthetic 123-bus TX123BT system, the nominal-load circuit-specific requirement is 317.14 MW, compared with 4141.51 MW for a common-factor allocation, representing a reduction of 92.34% in summed thermal increments. Both frozen vectors preserve the zero-shedding DLR reference load-shedding limits over all 26,280 training hours without further upgrades. Optimized two-, four-, and eight-group allocations confirm the role of spatial resolution. In the separate retrofit comparison, both investment families retain 37 circuit additions and satisfy normal and single-circuit corrective security over the same training chronology. Under the DC planning model, DLR reduces further construction from two circuits to one, providing approximately USD 6.11 million in net annualized benefit, including monitoring: 55.32% of additional retrofit expenditure and 1.74% of total capital.
Funding
- State Grid Tianjin Electric Power Company
Cite
APA
Liu, Z., Song, J., Zhang, T., Li, Y., & Li, T. (2026). Coordinated Dynamic Line Rating and Transmission Expansion Planning with Reliable Thermal-Capacity Assessment in Critical Transmission Hours. Electronics, 15(22), 5299. https://doi.org/10.3390/electronics15225299
Vancouver
Liu Z, Song J, Zhang T, Li Y, Li T. Coordinated Dynamic Line Rating and Transmission Expansion Planning with Reliable Thermal-Capacity Assessment in Critical Transmission Hours. Electronics. 2026;15(22):5299. doi:10.3390/electronics15225299
BibTeX
@article{Liu2026,
author = {Liu, Zhongyi and Song, Jia and Zhang, Tianyu and Li, Yuanyuan and Li, Tianxiang},
title = {Coordinated Dynamic Line Rating and Transmission Expansion Planning with Reliable Thermal-Capacity Assessment in Critical Transmission Hours},
journal = {Electronics},
year = {2026},
volume = {15},
number = {22},
pages = {5299},
doi = {10.3390/electronics15225299}
}
EUVIMED