Calculation Method of Ground Settlement Caused by Mechanical Construction in Metro-Connected Aisle
Buildings · 16.04.2026 · 16 (8) · 1580
DOI: 10.3390/buildings16081580 ↗Kurz gefasst
Fachartikel in der Zeitschrift Buildings, online erschienen am 16.04.2026. Verfasst von Yueqiang Duan und 6 weiteren Autor:innen. Die Arbeit nennt 46 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: National Natural Science Foundation of China, Key Research and Development Program of Science and Technology in Gansu Province, Science and Technology Development Project of China First Highway Engineering Co., LTD..
Abstract (Originalsprache)
Mechanical construction of metro-connected aisles is a novel construction method in the field of metro engineering, and it is being gradually applied to practical projects at present. However, current research predominantly focuses on the mechanical response of tunnel structures, with insufficient theoretical investigations into ground settlement. To study the ground settlement law caused by the mechanical construction of the metro-connected aisle, the ground settlement was divided into the superposition of settlement caused by the construction of the main shield tunnels and the connected aisle. The modified Peck formula was used to calculate the ground settlement caused by tunnel excavation. Based on the integration of the Mindlin solution, the ground settlement caused by the jacking force of the cutterhead was solved, and the three-dimensional calculation formula for ground settlement was derived. Taking the NO. 1 connected aisle of Shenzhen Metro Line 8 as the research object, the accuracy of the calculation formula was verified through comparative analysis with three-dimensional numerical simulation results and in situ monitoring data, and good agreement was observed. The research results indicate that after the construction of a connected aisle, a wedge-shaped surface appears on the settlement surface at the location of the connected aisle. The surface settlement curve presents a “U”—shaped distribution; as the depth increases, the stratum settlement curve presents a “W”—shaped distribution. The stratum disturbance caused by the connected aisle is more significant in its longitudinal direction than in the transverse direction. The theoretical calculation results show that the maximum surface settlement generated by the construction of the connected aisle is 0.61 mm, accounting for about 15.6% of the total settlement value (3.9 mm), and is far below the control value adopted by Shenzhen Metro. The calculation formula proposed in this article can be used to evaluate the surface settlement caused by the construction of connected aisles.
Förderung
- National Natural Science Foundation of China
- Key Research and Development Program of Science and Technology in Gansu Province
- Science and Technology Development Project of China First Highway Engineering Co., LTD.
- Science and Technology Development Project of China Railway Design Co., LTD.
Zitieren
APA
Duan, Y., Wang, M., Wang, J., Guo, Y., Chang, F., Zhang, B., & Sun, W. (2026). Calculation Method of Ground Settlement Caused by Mechanical Construction in Metro-Connected Aisle. Buildings, 16(8), 1580. https://doi.org/10.3390/buildings16081580
Vancouver
Duan Y, Wang M, Wang J, Guo Y, Chang F, Zhang B, et al. Calculation Method of Ground Settlement Caused by Mechanical Construction in Metro-Connected Aisle. Buildings. 2026;16(8):1580. doi:10.3390/buildings16081580
BibTeX
@article{Duan2026,
author = {Duan, Yueqiang and Wang, Maolei and Wang, Jinghe and Guo, Yuxiang and Chang, Fa and Zhang, Boyuan and Sun, Weiyu},
title = {Calculation Method of Ground Settlement Caused by Mechanical Construction in Metro-Connected Aisle},
journal = {Buildings},
year = {2026},
volume = {16},
number = {8},
pages = {1580},
doi = {10.3390/buildings16081580}
}
EUVIMED