EUVIMEDEUVIMED entdecken
Open Access · CC BY 4.0

Improving Cost Contingency Estimation in Infrastructure Projects with Artificial Neural Networks and a Complexity Index

Michael C. P. Sing, Qiuwen Ma, Qinhuan Gu

Applied Sciences · 24.03.2025 · 15 (7) · 3519

DOI: 10.3390/app15073519 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Applied Sciences, online erschienen am 24.03.2025. Verfasst von Michael C. P. Sing und 2 weiteren Autor:innen. Die Arbeit wurde bisher 8-mal zitiert (Crossref) und nennt 64 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: PolyU BRE Incentive Scheme.

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

Machine learning (ML) algorithms have been developed for cost performance prediction in the form of single-point estimates where they provide only a definitive value. This approach, however, often overlooks the vital influence project complexity exerts on estimation accuracy. This study addresses this limitation by presenting ML models that include interval predictions and integrating a complexity index that accounts for project size and duration. Utilizing a database of 122 infrastructure projects from public works departments totaling HKD 5465 billion (equivalent to USD 701 billion), this study involved training and evaluating seven ML algorithms. Artificial neural networks (ANNs) were identified as the most effective, and the complexity index integration increased the R2 for ANN-based single-point estimation from 0.808 to 0.889. In addition, methods such as bootstrapping and Monte Carlo dropout were employed for interval predictions, which resulted in significant improvements in prediction accuracy when the complexity index was incorporated. These findings not only advance the theoretical framework of ML algorithms for cost contingency prediction by implementing interval predictions but also provide practitioners with improved ML-based tools for more accurate infrastructure project cost performance predictions.

Förderung

  • PolyU BRE Incentive Scheme

Zitieren

APA

Sing, M. C. P., Ma, Q., & Gu, Q. (2025). Improving Cost Contingency Estimation in Infrastructure Projects with Artificial Neural Networks and a Complexity Index. Applied Sciences, 15(7), 3519. https://doi.org/10.3390/app15073519

Vancouver

Sing MCP, Ma Q, Gu Q. Improving Cost Contingency Estimation in Infrastructure Projects with Artificial Neural Networks and a Complexity Index. Applied Sciences. 2025;15(7):3519. doi:10.3390/app15073519

BibTeX
@article{Sing2025,
  author = {Sing, Michael C. P. and Ma, Qiuwen and Gu, Qinhuan},
  title = {Improving Cost Contingency Estimation in Infrastructure Projects with Artificial Neural Networks and a Complexity Index},
  journal = {Applied Sciences},
  year = {2025},
  volume = {15},
  number = {7},
  pages = {3519},
  doi = {10.3390/app15073519}
}
Kostenlos starten →