Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Considering Flexible Resource Profiles
Applied Sciences · 26.02.2024 · 14 (5) · 1921
DOI: 10.3390/app14051921 ↗Kurz gefasst
Fachartikel in der Zeitschrift Applied Sciences, online erschienen am 26.02.2024. Verfasst von Xu Luo und 4 weiteren Autor:innen. Die Arbeit wurde bisher 13-mal zitiert (Crossref) und nennt 37 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0).
Abstract (Originalsprache)
This paper addresses a novel multi-skill resource-constrained project scheduling problem with flexible resource profiles (F-MSRCPSP), in which the resource allocation of each activity consists of a certain number of discrete resources and is allowed to be adjusted over its duration. The F-MSRCPSP aims, therefore, to determine the flexible resource profile of each activity to minimize the make-span and total cost simultaneously. Then, a hybrid multi-objective fruit fly optimization algorithm is proposed to handle the concerned problem. In the proposed algorithm, two flexible parallel and serial schedule generation schemes are introduced, aiming to schedule activities and adjust allocated resource combinations. Additionally, two heuristic strategies are proposed to effectively select suitable resource combinations for activities. Moreover, a series of operators has been developed, including the rejoining operator, empirical re-arrangement operator, and empirical re-selection operator. These operators aim to accelerate the convergence speed and enhance the exploration of the proposed algorithm. Finally, the orthogonal test is used to select the optimal parameter combination, and comparative experiments based on tests with different scales are conducted, along with a t-test. The experimental results demonstrate that MOFOA-HS is effective in solving the F-MSRCPSP.
Zitieren
APA
Luo, X., Guo, S., Du, B., Luo, X., & Guo, J. (2024). Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Considering Flexible Resource Profiles. Applied Sciences, 14(5), 1921. https://doi.org/10.3390/app14051921
Vancouver
Luo X, Guo S, Du B, Luo X, Guo J. Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Considering Flexible Resource Profiles. Applied Sciences. 2024;14(5):1921. doi:10.3390/app14051921
BibTeX
@article{Luo2024,
author = {Luo, Xu and Guo, Shunsheng and Du, Baigang and Luo, Xinhao and Guo, Jun},
title = {Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Considering Flexible Resource Profiles},
journal = {Applied Sciences},
year = {2024},
volume = {14},
number = {5},
pages = {1921},
doi = {10.3390/app14051921}
}
EUVIMED