Preemptive and non-preemptive multi-skill multi-mode resource-constrained project scheduling problems considering sustainability and energy consumption: A comprehensive mathematical model

Reza Shahabi-Shahmiri, Reza Tavakkoli-Moghaddam, Alexandre Dolgui, Seyed-Ali Mirnezami, Mohammad Ghasemi, Mahsa Ahmadi

Journal of Environmental Management · 2024-09 · 367 · 121986

DOI: 10.1016/j.jenvman.2024.121986 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Journal of Environmental Management, 2024-09. Verfasst von Reza Shahabi-Shahmiri und 5 weiteren Autor:innen. Beteiligte Einrichtung: School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran. Electronic address: reza_shahabi011@ut.ac.ir. Hauptthemen laut MEDLINE: Models, Theoretical, Algorithms. Die Arbeit wurde bisher 22-mal zitiert (Crossref) und nennt 113 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0).

AbstractSchlagwörterBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

Modern project managers cope with significant challenges to schedule and control projects considering dynamic environments, frequent uncertainties, strict project deadlines, and stricter sustainable requirements above all. Sustainability taking into account resource utilization has been recently associated with project management. Hence, this paper presents a new mixed-integer linear programming (MILP) model with two objectives for a resource-constrained project scheduling problem (RCPSP) with multiple skills and multiple modes, assuming preemptive and non-preemptive activities in an uncertain environment. Given the importance of sustainable developments in projects, the considered objectives are to maximize job opportunities and minimize project duration, resource costs, and total energy consumption. To deal with the model, an AUGNMECON2VIKOR algorithm is utilized to create Pareto solutions. In this model, project activities can be crashed by allocating extra resources. Furthermore, multi-skill resources are used to perform project activities. This study also investigates the impact of these resources on project scheduling. To deal with uncertain circumstances, a fuzzy chance-constrained programming method is employed to develop a robust possibilistic programming model. With respect to the increasing significance of sustainability in project management, this study pioneers the examination of the impact of sustainable factors on project scheduling. Finally, the proposed formulation is validated using instances from the well-known PSPLIB and MMLIB test sets. Finally, a comparison is drawn between the presented solution method considering AUGMECON2VIKOR and AUGMECON2.

Schlagwörter

MeSH-Schlagwörter (MEDLINE)

Models, TheoreticalAlgorithmsConservation of Natural ResourcesSustainable Development

Stichwörter der Autor:innen

Activity preemption and crashingEnergy consumptionProject schedulingRobust chance-constrained programmingSustainability

Autor:innen und Institutionen

  • School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran. Electronic address: reza_shahabi011@ut.ac.ir.
  • School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran; Research Center of Performance and Productivity Analysis, Istinye University, Istanbul, Turkey. Electronic address: tavakoli@…
  • IMT Atlantique, LS2N - CNRS, La Chantrerie, Nantes, France. Electronic address: alexandre.dolgui@imt-atlantique.fr.
  • Department of Industrial Engineering, Faculty of Engineering, Shahed University, Tehran, Iran. Electronic address: mirnezamiali@gmail.com.
  • School of Information Technology, Deakin University, Geelong, Australia. Electronic address: mohammad.ghasemi@research.deakin.edu.au.
  • School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran. Electronic address: mahsa.ahmadi@ut.ac.ir.

Zitieren

APA

Shahabi-Shahmiri, R., Tavakkoli-Moghaddam, R., Dolgui, A., Mirnezami, S. A., Ghasemi, M., & Ahmadi, M. (2024). Preemptive and non-preemptive multi-skill multi-mode resource-constrained project scheduling problems considering sustainability and energy consumption: A comprehensive mathematical model. Journal of Environmental Management, 367, 121986. https://doi.org/10.1016/j.jenvman.2024.121986

Vancouver

Shahabi-Shahmiri R, Tavakkoli-Moghaddam R, Dolgui A, Mirnezami SA, Ghasemi M, Ahmadi M. Preemptive and non-preemptive multi-skill multi-mode resource-constrained project scheduling problems considering sustainability and energy consumption: A comprehensive mathematical model. Journal of Environmental Management. 2024;367:121986. doi:10.1016/j.jenvman.2024.121986

BibTeX
@article{ShahabiShahmiri2024,
  author = {Shahabi-Shahmiri, Reza and Tavakkoli-Moghaddam, Reza and Dolgui, Alexandre and Mirnezami, Seyed-Ali and Ghasemi, Mohammad and Ahmadi, Mahsa},
  title = {Preemptive and non-preemptive multi-skill multi-mode resource-constrained project scheduling problems considering sustainability and energy consumption: A comprehensive mathematical model},
  journal = {Journal of Environmental Management},
  year = {2024},
  volume = {367},
  pages = {121986},
  doi = {10.1016/j.jenvman.2024.121986}
}