Fachartikel in der Zeitschrift Heuristic, online erschienen am 30.10.2026. Verfasst von Ardhila Fanny Damayanti und 1 weiteren Autor:innen. Der Volltext ist frei zugänglich (Open Access, CC BY-SA 4.0).
Abstract (Originalsprache)
CV. ABC is a manufacturing company engaged in the production of woven mats made of raffia rope through the extrusion process. In the implementation of its production, the company experienced obstacles in the form of high levels of damage to the extrusion machine and the length of downtime, which had an impact on the achievement of production targets not optimally. In the period from August 2025 to January 2026, there was a difference between the target and the realization of production of 900 - 1,400 pcs, with a total of 145 maintenance activities and a total downtime of 162 hours. In addition, defective products in the form of raffia rope were found to be 75 kg per day or around 3.57% of total production. This study aims to identify the types of failures that have the highest level of risk through the Failure Mode and Effects Analysis (FMEA) method and formulate the right machine maintenance strategy with the Reliability Centered Maintenance (RCM) approach. The results of the FMEA evaluation identified Filters/Filters, Die, Screws, Thrust Bearings, and Hoppers as critical components based on the highest Risk Priority Number (RPN) values. Meanwhile, the RCM analysis resulted in preventive maintenance recommendations with Mean Time To Failure (MTTF) values of 11.44 days for Filters/Filters, 20.25 days for Die, 20.29 days for Screws, and 33.25 days for Thrust Bearings. The implementation of the preventive maintenance schedule planned for the July-December 2026 period is expected to improve engine reliability, minimize downtime, and maintain a smooth production process, with an estimated total maintenance cost of IDR 53,500,000.
Zitieren
APA
Damayanti, A. F., & Widiasih, W. (2026). Failure Analysis and Priority Determination of Maintenance of Raffia Rope Extrusion Machine Using the FMEA Method. Heuristic, 269-280. https://doi.org/10.30996/heuristic.v23i2.133612
Vancouver
Damayanti AF, Widiasih W. Failure Analysis and Priority Determination of Maintenance of Raffia Rope Extrusion Machine Using the FMEA Method. Heuristic. 2026:269-280. doi:10.30996/heuristic.v23i2.133612
BibTeX
@article{Damayanti2026,
author = {Damayanti, Ardhila Fanny and Widiasih, Wiwin},
title = {Failure Analysis and Priority Determination of Maintenance of Raffia Rope Extrusion Machine Using the FMEA Method},
journal = {Heuristic},
year = {2026},
pages = {269--280},
doi = {10.30996/heuristic.v23i2.133612}
}