Enhanced repetitive scheduling formulation for meeting deadlines and resource constraints in linear and scattered projects
Canadian Journal of Civil Engineering · 01.03.2023 · 50 (3) · 172-183
DOI: 10.1139/cjce-2022-0029 ↗Kurz gefasst
Fachartikel in der Zeitschrift Canadian Journal of Civil Engineering, erschienen am 01.03.2023. Verfasst von Kareem Mostafa und 2 weiteren Autor:innen. Die Arbeit wurde bisher 14-mal zitiert (Crossref) und nennt 25 Literaturangaben.
Abstract (Originalsprache)
The majority of civil infrastructure projects involve activities that are repeated across a number of linear units (e.g., highway sections) or scattered units (e.g., multi-bridge rehabilitations). For these projects, Critical Path Method (CPM)/line-of-balance (LOB) repetitive scheduling combines the benefits of CPM and LOB analyses to maintain work continuity across units, yet assumes simple sequential unit order and results in schedule delays for practical projects with non-identical units, constrained resources, and (or) strict deadlines. To improve CPM/LOB scheduling, this paper introduces powerful and easy-to-use enhancements, including (1) designed interruptions to reduce time gaps; (2) efficient resource-constrained first-come first-serve crew assignment; (3) crew adjustment loop to meet deadlines; and (4) representation of flexible unit sequence. These simplified enhancements computationally produce schedules that respect deadlines, individual resource limits, and desired sequence among units. Example projects are then presented to prove that the proposed enhancements offer flexible scheduling features that can meet the strict constraints of infrastructure projects.
Zitieren
APA
Mostafa, K., Ojulari, S., & Hegazy, T. (2023). Enhanced repetitive scheduling formulation for meeting deadlines and resource constraints in linear and scattered projects. Canadian Journal of Civil Engineering, 50(3), 172-183. https://doi.org/10.1139/cjce-2022-0029
Vancouver
Mostafa K, Ojulari S, Hegazy T. Enhanced repetitive scheduling formulation for meeting deadlines and resource constraints in linear and scattered projects. Canadian Journal of Civil Engineering. 2023;50(3):172-183. doi:10.1139/cjce-2022-0029
BibTeX
@article{Mostafa2023,
author = {Mostafa, Kareem and Ojulari, Sayeeda and Hegazy, Tarek},
title = {Enhanced repetitive scheduling formulation for meeting deadlines and resource constraints in linear and scattered projects},
journal = {Canadian Journal of Civil Engineering},
year = {2023},
volume = {50},
number = {3},
pages = {172--183},
doi = {10.1139/cjce-2022-0029}
}
EUVIMED