Adaptive Water Infrastructure Planning Under Permitting Delay: Management and Planning Lessons from the Santa Barbara Desalination Case
Journal of Management and Planning Research · 30.12.2025 · 2 · 188-196
DOI: 10.66033/jmpr2025-217 ↗Kurz gefasst
Fachartikel in der Zeitschrift Journal of Management and Planning Research, online erschienen am 30.12.2025. Verfasst von Spyros G. Tzafestas.
Abstract (Originalsprache)
Environmental permitting is often treated as a regulatory constraint external to infrastructure planning. In practice, however, permitting delay is a core managerial variable because it determines whether an organization can respond proportionately to changing system conditions or must instead commit capital in advance of demonstrated need. This article offers a structured management interpretation of the Santa Barbara desalination case analyzed by Zaniolo, Fletcher, and Mauter, using the source study’s published scenarios as evidence rather than presenting a new engineering simulation. The manuscript reframes the case as a planning problem centered on timing, institutional coordination, and decision triggers, and it shows why time to deployment (TTD) conditions the practical value of adaptive policy. In the source-reported Santa Barbara simulations, reducing TTD from 8 years to 4 years cuts average plant operating time from approximately 96% to 48% of the 50-year planning horizon, and reducing TTD to 2 years lowers average operating time to roughly 20%. When adaptive decommissioning is added at short TTD, operational and environmental costs can be reduced by as much as 85% relative to adaptive commissioning alone. By translating these source-reported results into a management and planning framework, the article identifies permitting speed, review coordination, and deployment predictability as central design variables in public-sector infrastructure management.
Zitieren
APA
Tzafestas, S. G. (2025). Adaptive Water Infrastructure Planning Under Permitting Delay: Management and Planning Lessons from the Santa Barbara Desalination Case. Journal of Management and Planning Research, 2, 188-196. https://doi.org/10.66033/jmpr2025-217
Vancouver
Tzafestas SG. Adaptive Water Infrastructure Planning Under Permitting Delay: Management and Planning Lessons from the Santa Barbara Desalination Case. Journal of Management and Planning Research. 2025;2:188-196. doi:10.66033/jmpr2025-217
BibTeX
@article{Tzafestas2025,
author = {Tzafestas, Spyros G.},
title = {Adaptive Water Infrastructure Planning Under Permitting Delay: Management and Planning Lessons from the Santa Barbara Desalination Case},
journal = {Journal of Management and Planning Research},
year = {2025},
volume = {2},
pages = {188--196},
doi = {10.66033/jmpr2025-217}
}
EUVIMED