Reevaluating Earned Value Formulas Across Project Types: A Critical Cross-Case Analysis

Shealan Hameed

Dijlah Journal of Engineering Sciences ISSN: 3078-9664, e-ISSN: 3078-9656 · 2026

DOI: 10.65204/djes.v3i3.697 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Dijlah Journal of Engineering Sciences ISSN: 3078-9664, e-ISSN: 3078-9656, 2026. Verfasst von Shealan Hameed.

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

Traditionally, Earned Value Management (EVM) has generally been applied as a standard methodology for project cost and/ or schedule performance dimension. Though with expansive institutionalization as a standard with the help of morals in project performance dimension as it concerns transnational project operation, are there project enterprises where, under the traditional Earned Value fashion, one couldn't calculate and/ or understand? The extensively applied Earned Value formula, which relies on specific probability of completion, has proven to affect in the severe conception of project performance, thereby distorting the Earned Value approach in project schedule performance dimension. This is because this paper seeks to offer a critical analysis of the conventional traditional Earned Value approach through the operation of the comparison of different kinds of project types: Software development, Professional Consulting Services, and Construction Projects. [1].[2]Once the criteria for performance confines have been linked, the applicable performance pointers similar as EV, PV, AC, CPI, SPI, and EAC can be assessed and compared. The viability of the effectiveness of these important EVM performance pointers can be estimated for the connection of EVM for fiscal performance; still, it cannot be relied upon for project performance. A marked difference has been noted between indicated performance indices and the real project execution realities, especially in those projects that show prominent schedule interdependencies and critical path sensitivity. In this regard, this study builds upon the area of project management theory by highlighting the structural short comings of traditional EV usage as well as the overall importance of the integration of schedules, predicated performance extension, risks, shaped activity weights, as well as critical path sense into the traditional systems of performance measurement.[3] [4]From the managerial position, the research results provide useful perceptivity to layout directors and associations on enhancing performance dimension delicacy and battling undesirable control signals. This work provides a practical engineering-oriented perspective for improving project control reliability in real execution environments. The proposed comparative analysis supports decision-making in engineering project management applications by highlighting actionable performance diagnosis mechanisms.[5]

Zitieren

APA

Hameed, S. (2026). Reevaluating Earned Value Formulas Across Project Types: A Critical Cross-Case Analysis. Dijlah Journal of Engineering Sciences ISSN: 3078-9664, e-ISSN: 3078-9656. https://doi.org/10.65204/djes.v3i3.697

Vancouver

Hameed S. Reevaluating Earned Value Formulas Across Project Types: A Critical Cross-Case Analysis. Dijlah Journal of Engineering Sciences ISSN: 3078-9664, e-ISSN: 3078-9656. 2026. doi:10.65204/djes.v3i3.697

BibTeX
@article{Hameed2026,
  author = {Hameed, Shealan},
  title = {Reevaluating Earned Value Formulas Across Project Types: A Critical Cross-Case Analysis},
  journal = {Dijlah Journal of Engineering Sciences ISSN: 3078-9664, e-ISSN: 3078-9656},
  year = {2026},
  doi = {10.65204/djes.v3i3.697}
}
Kostenlos starten →