Review of earned value management (EVM) methodology, its limitations, and applicable extensions
Journal of Management and Engineering Integration · 2019
DOI: 10.62704/10057/24251 ↗Kurz gefasst
Fachartikel in der Zeitschrift Journal of Management and Engineering Integration, 2019. Verfasst von Anisulrahman Nizam und 1 weiteren Autor:innen. Die Arbeit wurde bisher 6-mal zitiert (Crossref).
Abstract (Originalsprache)
Department of Defense (DoD) Instruction 5000.02 requires an Earned Value Management System (EVMS) compliant with ANSI/EIA-748 for all DoD cost or incentive contracts valued at or greater than $20M. Earned Value Management (EVM) integrates cost, schedule, and time to draw conclusions about current project status as well as make projections for future project status. Though EVM has been widely adopted on many projects, there are clear limitations indicated in the literature which ultimately inhibit the ability of EVM to become universally accepted as a best practice across all industries. In response, researchers have developed extensions such as Earned Schedule Management (ESM), Earned Duration Management (EDM), and Customer Earned Value (CEV). This paper addresses the evolution, limitations, and new extensions of EVM.
Zitieren
APA
Nizam, A., & Elshannaway, A. (2019). Review of earned value management (EVM) methodology, its limitations, and applicable extensions. Journal of Management and Engineering Integration. https://doi.org/10.62704/10057/24251
Vancouver
Nizam A, Elshannaway A. Review of earned value management (EVM) methodology, its limitations, and applicable extensions. Journal of Management and Engineering Integration. 2019. doi:10.62704/10057/24251
BibTeX
@article{Nizam2019,
author = {Nizam, Anisulrahman and Elshannaway, Ahmad},
title = {Review of earned value management (EVM) methodology, its limitations, and applicable extensions},
journal = {Journal of Management and Engineering Integration},
year = {2019},
doi = {10.62704/10057/24251}
}
EUVIMED