Implementation of Daily Takt in Construction: A Case Study of a Norwegian Residential Project
Lean Construction Journal · 09.03.2026 · 55-84
DOI: 10.60164/fkiv7ifd9 ↗Kurz gefasst
Fachartikel in der Zeitschrift Lean Construction Journal, online erschienen am 09.03.2026. Verfasst von Malin Furuli Munkvold und 2 weiteren Autor:innen.
Abstract (Originalsprache)
Question: What happens in the execution of a residential project when daily takt is introduced, and what specific experiences can be drawn to improve future projects?
Purpose
This paper examines the implementation of daily takt time in a residential construction project, focusing on how the takt plan was developed and executed. It explores the changes and challenges encountered when transitioning from weekly to daily takt and identifies lessons learned that can improve future use of takt planning. Research Method: Case study Findings: Daily takt introduced challenges such as reduced flexibility, complex coordination, and logistical issues. Key difficulties in the case project included poor planning, inaccurate workload estimates, insufficient subcontractor capacity, problems with digital tools, and limited space. However, with careful planning, subcontractor involvement, logistics alignment, and enhanced management support, daily takt can increase construction efficiency.
Limitations
The study’s generalizability is constrained by contextual factors, subjective data sources, market conditions, and the limited scope of existing research on the topic.
Implications
While daily takt can significantly improve workflow and efficiency in construction projects, it requires meticulous planning, robust subcontractor involvement, and enhanced management support. Value for practitioners: By presenting lessons learned, the paper serves as a guide for practitioners considering short takt times, helping them to anticipate challenges, refine planning processes, and enhance overall project execution. Keywords: lean construction, daily takt, takt planning, case study Paper type: Full Paper
Zitieren
APA
Munkvold, M. F., Lædre, O., & Drevland, F. (2026). Implementation of Daily Takt in Construction: A Case Study of a Norwegian Residential Project. Lean Construction Journal, 55-84. https://doi.org/10.60164/fkiv7ifd9
Vancouver
Munkvold MF, Lædre O, Drevland F. Implementation of Daily Takt in Construction: A Case Study of a Norwegian Residential Project. Lean Construction Journal. 2026:55-84. doi:10.60164/fkiv7ifd9
BibTeX
@article{Munkvold2026,
author = {Munkvold, Malin Furuli and Lædre, Ola and Drevland, Frode},
title = {Implementation of Daily Takt in Construction: A Case Study of a Norwegian Residential Project},
journal = {Lean Construction Journal},
year = {2026},
pages = {55--84},
doi = {10.60164/fkiv7ifd9}
}
EUVIMED