Building Information Modeling Using Cubicost TME for Electrical Quantity Take-Off and Website-Based Cost Estimation at BTN Ecopark Gandul
International Journal of Engineering Continuity · 07.08.2026 · 5 (2) · 85-100
DOI: 10.58291/ijec.v5i2.642 ↗Kurz gefasst
Fachartikel in der Zeitschrift International Journal of Engineering Continuity, online erschienen am 07.08.2026. Verfasst von Sugiarti Kimayah und 2 weiteren Autor:innen. Der Volltext ist frei zugänglich (Open Access, CC BY-SA 4.0).
Abstract (Originalsprache)
: Conventional quantity take-off (QTO) of electrical works relies on two-dimensional drawings and cannot capture the actual three-dimensional routing of feeder cables, cable trays, and cable ladders, causing volume and cost inaccuracy. This research optimizes electrical works QTO using Building Information Modeling (BIM) Cubicost Take-off for Mechanical and Electrical (TME) and implements the validated results into a website-based cost estimation system. Its novelty is an applied, integrated workflow connecting Cubicost TME-based electrical QTO, engineering verification under the General Requirements for Electrical Installations (PUIL) 2020/SNI 0225:2020, and web-based cost reporting within a single Indonesian case study; although each component is established, their end-to-end integration for electrical works is rarely reported. The contribution is a reproducible workflow that converts model-derived quantities into standard-verified, openly accessible cost information, repositioning engineering validation as an integral gate within QTO. Using a quantitative descriptive-comparative method at the BTN Ecopark Gandul project, the installation was modeled three-dimensionally and validated through voltage drop, ampacity, and power demand calculations. On the conventional baseline, BIM-based cable volumes are 8.59% lower with an identical panel count, and the BIM cost estimate is 3.95% lower; all routes satisfy the 5% voltage drop limit, peaking at 1.641%. On an equivalent net basis (after removing the 5% waste allowance present only in the conventional data), the volume deviation narrows to 4.02%, showing that about half of the gross gap reflects the waste allowance and the remainder genuine routing differences; the cost difference is thus an estimated, case-specific figure, not a confirmed saving.
Zitieren
APA
Kimayah, S., Siregar, M. R., & Taryo, T. (2026). Building Information Modeling Using Cubicost TME for Electrical Quantity Take-Off and Website-Based Cost Estimation at BTN Ecopark Gandul. International Journal of Engineering Continuity, 5(2), 85-100. https://doi.org/10.58291/ijec.v5i2.642
Vancouver
Kimayah S, Siregar MR, Taryo T. Building Information Modeling Using Cubicost TME for Electrical Quantity Take-Off and Website-Based Cost Estimation at BTN Ecopark Gandul. International Journal of Engineering Continuity. 2026;5(2):85-100. doi:10.58291/ijec.v5i2.642
BibTeX
@article{Kimayah2026,
author = {Kimayah, Sugiarti and Siregar, Masbah R.T. and Taryo, Taswanda},
title = {Building Information Modeling Using Cubicost TME for Electrical Quantity Take-Off and Website-Based Cost Estimation at BTN Ecopark Gandul},
journal = {International Journal of Engineering Continuity},
year = {2026},
volume = {5},
number = {2},
pages = {85--100},
doi = {10.58291/ijec.v5i2.642}
}
EUVIMED