Critical Path Analysis for Construction Schedule Optimization: RSGM UMSIDA Study Case

Izzul Manjulang Tunggal Panggayo, Andi Patriadi, Retno Hastijanti

Journal of Multidisciplinary Research · 17.04.2026 · 51-64

DOI: 10.56943/jmr.v5i2.939 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Journal of Multidisciplinary Research, online erschienen am 17.04.2026. Verfasst von Izzul Manjulang Tunggal Panggayo und 2 weiteren Autor:innen.

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

The development of educational infrastructure represents a fundamental pillar supporting human resource advancement in Indonesia. Universitas Muhammadiyah Sidoarjo, as a growing higher education institution, addresses the need for academic facilities through the construction of a dental hospital (RSGM), demonstrating its commitment to public health services. This project functions as a teaching hospital in collaboration with the Faculty of Medicine at UMSIDA, enabling medical students to conduct clinical practice. This study aims to determine the optimal project duration after acceleration and identify the required costs resulting from this acceleration. The research applied the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) to optimize construction scheduling. Results indicate that CPM effectively reduces project completion time from 147 weeks to 104 weeks, while PERT reduces it to 105 weeks, with additional costs of Rp 580,930,000.00 (3.85% of initial budget) and Rp 567,420,000.00 (3.76%) respectively. The PERT implementation, with critical path A-B-C-D-E-F-J, demonstrates a 99.99% probability of completing the project within 105 weeks. Overall, the acceleration efforts yield time savings of 43 weeks using CPM and 42 weeks using PERT, with PERT offering a more cost-efficient alternative. These findings validate the effectiveness of systematic network analysis approaches in educational healthcare facility construction, providing a replicable framework for similar infrastructure development projects in developing regions.

Zitieren

APA

Panggayo, I. M. T., Patriadi, A., & Hastijanti, R. (2026). Critical Path Analysis for Construction Schedule Optimization: RSGM UMSIDA Study Case. Journal of Multidisciplinary Research, 51-64. https://doi.org/10.56943/jmr.v5i2.939

Vancouver

Panggayo IMT, Patriadi A, Hastijanti R. Critical Path Analysis for Construction Schedule Optimization: RSGM UMSIDA Study Case. Journal of Multidisciplinary Research. 2026:51-64. doi:10.56943/jmr.v5i2.939

BibTeX
@article{Panggayo2026,
  author = {Panggayo, Izzul Manjulang Tunggal and Patriadi, Andi and Hastijanti, Retno},
  title = {Critical Path Analysis for Construction Schedule Optimization: RSGM UMSIDA Study Case},
  journal = {Journal of Multidisciplinary Research},
  year = {2026},
  pages = {51--64},
  doi = {10.56943/jmr.v5i2.939}
}
Kostenlos starten →