Analysis Repair End Voltage and shrink Technical with Reconfiguration Network 20 KV distribution on Feeder PT PLN (Persero) Service Unit Silago Customer (ULP) Sitiung
Dinasti Information and Technology · 2023
DOI: 10.38035/dit.v1i1.252 ↗Kurz gefasst
Fachartikel in der Zeitschrift Dinasti Information and Technology, 2023. Verfasst von Ferdian Pondri und 1 weiteren Autor:innen. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0).
Abstract (Originalsprache)
There is voltage drop at the tip feeder silago because length network feeder the resulted distribution Genre Power electricity to customer suboptimal . By Because That done analysis transfer burden network with method reconfigure network distribution voltage intermediate feeder the original syllabus is output from substation Connect (GH) Sungai Dareh Then moved to feeder river dareh that direct output from substation Main (GI) Lansek River with use ETAP application 19.01, so expected can repair voltage drop across the feeder sylago so that distribution Genre Power electricity to customer can be optimal.
Zitieren
APA
Pondri, F., & Sukardi, S. (2023). Analysis Repair End Voltage and shrink Technical with Reconfiguration Network 20 KV distribution on Feeder PT PLN (Persero) Service Unit Silago Customer (ULP) Sitiung. Dinasti Information and Technology. https://doi.org/10.38035/dit.v1i1.252
Vancouver
Pondri F, Sukardi S. Analysis Repair End Voltage and shrink Technical with Reconfiguration Network 20 KV distribution on Feeder PT PLN (Persero) Service Unit Silago Customer (ULP) Sitiung. Dinasti Information and Technology. 2023. doi:10.38035/dit.v1i1.252
BibTeX
@article{Pondri2023,
author = {Pondri, Ferdian and Sukardi, Sukardi},
title = {Analysis Repair End Voltage and shrink Technical with Reconfiguration Network 20 KV distribution on Feeder PT PLN (Persero) Service Unit Silago Customer (ULP) Sitiung},
journal = {Dinasti Information and Technology},
year = {2023},
doi = {10.38035/dit.v1i1.252}
}