Effects of Construction Delays in Road Projects on Quality of Work

Evans Kemboi Lamaon, Simpson Nyambane Osana, George Matheri

East African Journal of Engineering · 14.07.2026 · 9 (2) · 1-14

DOI: 10.37284/eaje.9.2.5339 ↗

Kurz gefasst

Fachartikel in der Zeitschrift East African Journal of Engineering, online erschienen am 14.07.2026. Verfasst von Evans Kemboi Lamaon und 2 weiteren Autor:innen. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0).

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

In the execution of various construction projects, challenges leading to delays and disruptions have been on the rise as various partners are involved in the construction industry. When such delays affect road construction, some sections may be open for traffic before all pavement layers are laid due to a lack of space for traffic diversions. This study evaluated an incomplete pavement structure that was open to traffic when its construction was hit with delays. The study employed visual surface inspection and field and laboratory tests as the primary source of data, and secondary data were collected from the authorities in charge of the project. The findings were that the granular crushed stone road base suffered distress associated with excessive axial load, such as fatigue cracking, potholes, and edge failures. The subsequent distresses were transferred to the underlying layers of sub-base and subgrade. The layers recorded lower Field Dry Density (FDD) and increased Moisture Content (MC). The subgrade material got finer and had high changes in moisture content, which is detrimental to any pavement structure. This affected their functionality, leading to severe pavement deterioration. The findings recommended the complete reconstruction of the pavement structure and further upscaling of pavement type to cater to the high traffic volume projected. There is a need for better project planning to ensure the completion of road projects, especially in urban settlements where space for traffic diversion is limited. Incomplete pavement structures should be well protected from excessive traffic and ingress of moisture content, more so when unbound granular materials are used as subgrade. The value of resources spent on any road project is recovered if projects are completed in a timely manner to serve the intended purposes, which is improving the economy of the country.

Zitieren

APA

Lamaon, E. K., Osana, S. N., & Matheri, G. (2026). Effects of Construction Delays in Road Projects on Quality of Work. East African Journal of Engineering, 9(2), 1-14. https://doi.org/10.37284/eaje.9.2.5339

Vancouver

Lamaon EK, Osana SN, Matheri G. Effects of Construction Delays in Road Projects on Quality of Work. East African Journal of Engineering. 2026;9(2):1-14. doi:10.37284/eaje.9.2.5339

BibTeX
@article{Lamaon2026,
  author = {Lamaon, Evans Kemboi and Osana, Simpson Nyambane and Matheri, George},
  title = {Effects of Construction Delays in Road Projects on Quality of Work},
  journal = {East African Journal of Engineering},
  year = {2026},
  volume = {9},
  number = {2},
  pages = {1--14},
  doi = {10.37284/eaje.9.2.5339}
}
Kostenlos starten →