Dam Failure Mechanism and Risk Assessment Under Extreme Rainfall Conditions: Case Study of Hubuling Reservoir

Xixuan Zhang, Chao Yin, Jingjing Li, Tianqi Sun

Water · 07.06.2026 · 18 (12) · 1396

DOI: 10.3390/w18121396 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Water, online erschienen am 07.06.2026. Verfasst von Xixuan Zhang und 3 weiteren Autor:innen. Die Arbeit nennt 41 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: National Natural Science Foundation of China, Natural Science Foundation of Shandong Province.

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

To reveal the overtopping dam-break mechanism under extreme rainfall conditions and assess downstream flood risk, a series of dam-break flume tests, flood routing simulations and inundation risk assessments were conducted. Using the Hubuling Reservoir in Rizhao City, Shandong Province as a case study, a circulating extreme rainfall dam-break flume system with a controllable reservoir water level was constructed at a geometric similarity scale of 1:70. Four test conditions were designed: no rainfall and 50-year, 100-year and 2000-year rainfall return periods. Pore water pressure, earth pressure and water content sensors were embedded in critical dam sections to monitor real-time internal dynamic responses. The results show that, due to the combined effect of the highest rainfall intensity, rapid reservoir water-level rise, progressive infiltration-induced weakening and concentrated surface erosion, a dam-break occurs only under the 2000-year rainfall return period. The failure process is divided into four stages: initial infiltration, slope surface scour, overtopping initiation and rapid breach development. Based on dam-break parameters obtained by physical model tests, a two-dimensional numerical using HEC-RAS was conducted. The results show that, under the 2000-year rainfall return period, the flood reaches the downstream area at 80 min after dam failure. The maximum inundation area reaches 15.20 km2 at 200 min, with a maximum inundation depth of 11.80 m and a maximum inundation duration of 144 h. By integrating the maximum inundation depth, inundation duration and land use conditions, the expected economic loss is estimated to be 690 million yuan. The results provide important support for dam-break early warnings, emergency management and disaster mitigation of similar small- and medium-sized reservoirs.

Förderung

  • National Natural Science Foundation of China
  • Natural Science Foundation of Shandong Province

Zitieren

APA

Zhang, X., Yin, C., Li, J., & Sun, T. (2026). Dam Failure Mechanism and Risk Assessment Under Extreme Rainfall Conditions: Case Study of Hubuling Reservoir. Water, 18(12), 1396. https://doi.org/10.3390/w18121396

Vancouver

Zhang X, Yin C, Li J, Sun T. Dam Failure Mechanism and Risk Assessment Under Extreme Rainfall Conditions: Case Study of Hubuling Reservoir. Water. 2026;18(12):1396. doi:10.3390/w18121396

BibTeX
@article{Zhang2026,
  author = {Zhang, Xixuan and Yin, Chao and Li, Jingjing and Sun, Tianqi},
  title = {Dam Failure Mechanism and Risk Assessment Under Extreme Rainfall Conditions: Case Study of Hubuling Reservoir},
  journal = {Water},
  year = {2026},
  volume = {18},
  number = {12},
  pages = {1396},
  doi = {10.3390/w18121396}
}
Kostenlos starten →