Influence of the Large-Span Pile-Beam-Arch Construction Method on the Surface Deformation of a Metro Station in the Silty Clay–Pebble Composite Stratum
Materials · 06.04.2023 · 16 (7) · 2934
DOI: 10.3390/ma16072934 ↗Kurz gefasst
Fachartikel in der Zeitschrift Materials, online erschienen am 06.04.2023. Verfasst von Tao Li und 6 weiteren Autor:innen. Beteiligte Einrichtung: School of Mechanics and Civil Engineering, China University of Mining and Technology, Beijing 100083, China. Die Arbeit wurde bisher 5-mal zitiert (Crossref) und nennt 28 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: the National Natural Science Foundation of China, the National Key Research and Development Program of the 13th Five-Year Plan of China, the Fundamental Research Fund for the Central Universities.
Abstract (Originalsprache)
The Pile-beam-arch (PBA) method is a new and effective construction method for the urban metro station. It is the key to ensuring the safe construction of the station to clarify the influence of PBA method construction on surface deformation under unfavorable geological and large span conditions. Based on a station of Beijing subway, this paper studies the surface deformation law of the large-span PBA method in different construction stages under silty clay–pebble composite stratum by means of FLAC 3D numerical analysis and field monitoring of level. Then the influence of the excavation scheme of the pilot tunnel and the construction scheme of the secondary lining of the arch on the surface deformation is simulated and analyzed. The results show that, through numerical simulation, the ratio of pilot tunnel excavation: pile-beam construction: vault initial support construction: vault secondary lining construction is about 5:1.1:3.3:0.6. The settlement deformation mainly occurs in the excavation stage of the pilot tunnel. Through the comparative analysis of the field monitoring results and the numerical simulation results, it can be seen that the two results are highly consistent, which verifies the accuracy of the numerical simulation results. The pilot tunnel excavation scheme of excavating the middle first and then excavating both sides, first through the upper layer and then through the lower layer, and the scheme of one-time construction of the secondary lining of the arch are better. The research results promote the further maturity and perfection of large-span PBA method construction under unfavorable geology and provide reference for similar projects.
Schlagwörter
Stichwörter der Autor:innen
Autor:innen und Institutionen
- School of Mechanics and Civil Engineering, China University of Mining and Technology, Beijing 100083, China.
- Stage Key Laboratory for Geomechanics and Deep Underground Engineering, China University of Mining and Technology, Beijing 100083, China.
- Beijing Municipal Construction Group Co., Ltd., Beijing 100032, China.
Förderung
- the National Natural Science Foundation of China
- the National Key Research and Development Program of the 13th Five-Year Plan of China
- the Fundamental Research Fund for the Central Universities
- the Study and Application of 3D Dynamic Control and Construction Technology of Shield Passing Under Concentrated Risk Area
- the Yue qi Young Scholars of China University of Mining and Technology-Beijing
- National Natural Science Foundation of China
- National Key Research and Development Program of the 13th Five-Year Plan of China
- Fundamental Research Fund for the Central Universities
Zitieren
APA
Li, T., Li, Y., Yang, T., Hou, R., Gao, Y., Liu, B., & Qiao, G. (2023). Influence of the Large-Span Pile-Beam-Arch Construction Method on the Surface Deformation of a Metro Station in the Silty Clay–Pebble Composite Stratum. Materials, 16(7), 2934. https://doi.org/10.3390/ma16072934
Vancouver
Li T, Li Y, Yang T, Hou R, Gao Y, Liu B, et al. Influence of the Large-Span Pile-Beam-Arch Construction Method on the Surface Deformation of a Metro Station in the Silty Clay–Pebble Composite Stratum. Materials. 2023;16(7):2934. doi:10.3390/ma16072934
BibTeX
@article{Li2023,
author = {Li, Tao and Li, Yue and Yang, Tengyu and Hou, Rui and Gao, Yuan and Liu, Bo and Qiao, Guogang},
title = {Influence of the Large-Span Pile-Beam-Arch Construction Method on the Surface Deformation of a Metro Station in the Silty Clay–Pebble Composite Stratum},
journal = {Materials},
year = {2023},
volume = {16},
number = {7},
pages = {2934},
doi = {10.3390/ma16072934}
}
EUVIMED