EUVIMEDEUVIMED entdecken
Open Access · CC BY-SA 4.0

Time Cost Trade-Off Analysis on The Sumobito Health Center Rehabilitation Project

Muhammad Rizkie Firmansyah, Nur Kholis, Meriana Wahyu Nugroho, Titin Sundari

Journal Innovation of Civil Engineering (JICE) · 24.01.2026 · 6 (2) · 208-218

DOI: 10.33474/jice.v6i2.21031 ↗

Kurz gefasst

Fachartikel in der Zeitschrift Journal Innovation of Civil Engineering (JICE), online erschienen am 24.01.2026. Verfasst von Muhammad Rizkie Firmansyah und 3 weiteren Autor:innen. Der Volltext ist frei zugänglich (Open Access, CC BY-SA 4.0).

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

This research examines ways to accelerate projects using the Time Cost Trade-Off (TCTO) method, supported by Primavera P6 software. The goal is to find the best balance between time and cost for rehabbing the Sumobito Health Center building in Jombang, a key public health spot that needs to be done faster without blowing the original budget. It zooms in on the main structural tasks along the critical path, pitting two speedup options against each other: one, tacking on 3 extra hours of overtime daily; two, boosting the workforce. The simulation results, laid out side by side, reveal that both approaches cut the project to 135 working days, shaving 15 days off the usual 150-day timeline. On the money side, the overtime route comes to Rp 4,004,863,761.46 (excluding VAT), which is cheaper than the worker-boosting plan at Rp 4,031,275,898.99 (excluding VAT). From the charts, overtime comes out on top as the smartest move, slashing the schedule while keeping expenses under the baseline budget. Overall, this study offers a practical, data-backed framework for contractors and project teams to identify effective, measurable ways to fast-track rehab jobs in public health buildings. Keywords: Critical Path; Time Cost Trade-Off; TCTO; Primavera P6; Project Acceleration; Time and Cost Optimization.

Zitieren

APA

Firmansyah, M. R., Kholis, N., Nugroho, M. W., & Sundari, T. (2026). Time Cost Trade-Off Analysis on The Sumobito Health Center Rehabilitation Project. Journal Innovation of Civil Engineering (JICE), 6(2), 208-218. https://doi.org/10.33474/jice.v6i2.21031

Vancouver

Firmansyah MR, Kholis N, Nugroho MW, Sundari T. Time Cost Trade-Off Analysis on The Sumobito Health Center Rehabilitation Project. Journal Innovation of Civil Engineering (JICE). 2026;6(2):208-218. doi:10.33474/jice.v6i2.21031

BibTeX
@article{Firmansyah2026,
  author = {Firmansyah, Muhammad Rizkie and Kholis, Nur and Nugroho, Meriana Wahyu and Sundari, Titin},
  title = {Time Cost Trade-Off Analysis on The Sumobito Health Center Rehabilitation Project},
  journal = {Journal Innovation of Civil Engineering (JICE)},
  year = {2026},
  volume = {6},
  number = {2},
  pages = {208--218},
  doi = {10.33474/jice.v6i2.21031}
}
Kostenlos starten →