Root Caused Failure Analysis Deodorizer Column at Expansion Bellow and Vacuum Chamber Connection to Column in Refinery Plant
Jurnal Praktik Keinsinyuran · 26.11.2025 · 2 (05) · 573-584
DOI: 10.25170/jpk.v2i05.6987 ↗Kurz gefasst
Fachartikel in der Zeitschrift Jurnal Praktik Keinsinyuran, online erschienen am 26.11.2025. Verfasst von Muhammad Adyutatama und 1 weiteren Autor:innen.
Abstract (Originalsprache)
Vacuum chamber that connecting the deodorizer column to the condenser had collapsed. The leaks were potentially occurring prior to the collapse of the vacuum chamber. The loading and unloading operation could make a fluctuating dynamic stress. In addition to the fluctuating dynamic stresses, fatigue failure mechanism had occured. The crack developed and gradually propagated in the welded joints which welded on the site due to it was proved have low mechanical properties as shown in tensile test. Follow the welding procedure specification (WPS) document, inspect the preparation of the welding process to ensure that the single-V groove is being preparedappropriately, inspect the weld during and/or after the welding process to ensure that it has achieved complete joint penetration and employ another non-destructive testing method, such as radiography, to verify the completeness of the joint penetration are recommended to prevent the similar failure in the future.
Zitieren
APA
Adyutatama, M., & Sutanto, H. (2025). Root Caused Failure Analysis Deodorizer Column at Expansion Bellow and Vacuum Chamber Connection to Column in Refinery Plant. Jurnal Praktik Keinsinyuran, 2(05), 573-584. https://doi.org/10.25170/jpk.v2i05.6987
Vancouver
Adyutatama M, Sutanto H. Root Caused Failure Analysis Deodorizer Column at Expansion Bellow and Vacuum Chamber Connection to Column in Refinery Plant. Jurnal Praktik Keinsinyuran. 2025;2(05):573-584. doi:10.25170/jpk.v2i05.6987
BibTeX
@article{Adyutatama2025,
author = {Adyutatama, Muhammad and Sutanto, Hadi},
title = {Root Caused Failure Analysis Deodorizer Column at Expansion Bellow and Vacuum Chamber Connection to Column in Refinery Plant},
journal = {Jurnal Praktik Keinsinyuran},
year = {2025},
volume = {2},
number = {05},
pages = {573--584},
doi = {10.25170/jpk.v2i05.6987}
}
EUVIMED