Calculation of additional load and deformation of the receiving well enclosure structure caused by shield tunneling

Li Xin iD, Li-Guang Chen, Tong Li, Yi-Lin Yu, Bo Wu

PLOS ONE · 2024

DOI: 10.1371/journal.pone.0297912 ↗

Kurz gefasst

Fachartikel in der Zeitschrift PLOS ONE, 2024. Verfasst von Li Xin und 4 weiteren Autor:innen. Beteiligte Einrichtung: China Construction Municipal Engineering Corporation Limited, Beijing, China. Hauptthemen laut MEDLINE: Engineering, Protective Devices. Die Arbeit nennt 26 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0).

AbstractSchlagwörterBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

The bulkhead additional thrust during shield tunneling, the force of friction between shield and soil, and the additional grouting pressure can cause additional stress in the surrounding soil, thereby disturbing existing buildings and structures. However, few studies focused on the disturbance situation when the shield tunneling machine approaches the receiving well. If the additional stress and deformation of the receiving well are too excessive, it could result in the collapse of the receiving well. Based on the two-stage method, this study derived the calculation formula of the additional stress and deformation of the receiving well enclosure structure caused by shield tunneling. Taking a shield machine receiving engineering as the context, this study established a numerical simulation model and compared theoretical calculation, the results of numerical simulation model and on-site monitoring data. Finally, the additional stress of the receiving well is analyzed. The research findings demonstrate that the theoretical prediction results, numerical simulation calculation results, and on-site monitoring data exhibit relatively small calculation errors, which validated the applicability of the theoretical prediction formula and numerical simulation model. As the distance between the shield machine and the receiving well decreases, the disturbance to the receiving well increases sharply. When the distance between the cutter head and the receiving well is less than three times the shield length, it is crucial to enhance the deformation monitoring of the receiving well. The primary factors affecting the additional load and deformation of the receiving well enclosure structure are the force of friction between shield and soil and the additional thrust of the cutterhead. The disturbance caused by the additional grouting pressure on the enclosure structure can be ignored.

Schlagwörter

MeSH-Schlagwörter (MEDLINE)

EngineeringProtective DevicesComputer SimulationFrictionSoil

Substanzen

Soil

Autor:innen und Institutionen

  • China Construction Municipal Engineering Corporation Limited, Beijing, China.
  • China Construction First Group Corporation Limited, Beijing, China.

ORCID-Profile: Li Xin

Zitieren

APA

Xin, L., Chen, L. G., Li, T., Yu, Y. L., & Wu, B. (2024). Calculation of additional load and deformation of the receiving well enclosure structure caused by shield tunneling. PLOS ONE. https://doi.org/10.1371/journal.pone.0297912

Vancouver

Xin L, Chen LG, Li T, Yu YL, Wu B. Calculation of additional load and deformation of the receiving well enclosure structure caused by shield tunneling. PLOS ONE. 2024. doi:10.1371/journal.pone.0297912

BibTeX
@article{Xin2024,
  author = {Xin, Li and Chen, Li-Guang and Li, Tong and Yu, Yi-Lin and Wu, Bo},
  title = {Calculation of additional load and deformation of the receiving well enclosure structure caused by shield tunneling},
  journal = {PLOS ONE},
  year = {2024},
  doi = {10.1371/journal.pone.0297912}
}
Kostenlos starten →