Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis
Advances in Civil Engineering · 16.06.2023 · 2023 · 1-21
DOI: 10.1155/2023/5525655 ↗Kurz gefasst
Fachartikel in der Zeitschrift Advances in Civil Engineering, erschienen am 16.06.2023. Verfasst von Shen Zhang und 1 weiteren Autor:innen. Die Arbeit wurde bisher 6-mal zitiert (Crossref) und nennt 32 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: Ministry of Housing and Urban-Rural Development.
Abstract (Originalsprache)
Progress management is an important scheme of construction management. In practical affairs, many unknown factors may lead to potential project delays and make the schedule risky. To address this issue, this paper proposes a data-driven construction progress evaluation method that employs a probabilistic reliability analysis with BIM to effectively quantify the risk of schedule delay. By identifying critical tasks and probable failure conditions in uncertain environments, this method enables project managers to take proactive measures to keep their projects on schedule. Through our case study, we have demonstrated that the proposed method is highly effective in dynamically evaluating the project progress with both accuracy and efficiency. Besides, this system offers a more efficient way for managers to gather information, evaluate progress, and identify critical tasks, and provides project managers with a data-driven understanding of the risks and uncertainties related to project schedules, enabling them to take proactive measures to minimize the potential delays and ensure successful project delivery.
Förderung
- Ministry of Housing and Urban-Rural Development
Zitieren
APA
Zhang, S., & Wang, X. (2023). Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis. Advances in Civil Engineering, 2023, 1-21. https://doi.org/10.1155/2023/5525655
Vancouver
Zhang S, Wang X. Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis. Advances in Civil Engineering. 2023;2023:1-21. doi:10.1155/2023/5525655
BibTeX
@article{Zhang2023,
author = {Zhang, Shen and Wang, Xingyu},
title = {Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis},
journal = {Advances in Civil Engineering},
year = {2023},
volume = {2023},
pages = {1--21},
doi = {10.1155/2023/5525655}
}
EUVIMED