AC-Guided Co-Expansion Planning of Power Grids Hosting High-Speed Railways

Anmar Arif

IEEE Access · 2026 · 14 · 168613-168632

DOI: 10.1109/access.2026.3748499 ↗

Kurz gefasst

Fachartikel in der Zeitschrift IEEE Access, 2026. Verfasst von Anmar Arif. Die Arbeit nennt 48 Literaturangaben. Der Volltext ist frei zugänglich (Open Access, CC BY 4.0). Gefördert von: Ongoing Research Funding Program, King Saud University, Riyadh, Saudi Arabia.

AbstractBibliografische AngabenZitierenVerwandte Studien

Abstract (Originalsprache)

High-speed railway (HSR) traction is among the fastest-growing electrical loads: tens of megawatts per substation, volatile on second timescales, and drawing substantial reactive power behind high-impedance traction transformers. Hosting grids were not planned for it, and no existing method determines the grid-side expansion such a load requires. This paper formulates and solves the co-expansion planning problem of a transmission grid hosting an HSR: a single mixed-integer linear program (MILP) co-optimizes new generation, storage on both sides of the traction interface, and a two-class reactive layer (dispatchable STATCOMs and mechanically switched capacitor banks) over a three-layer operating model linearized around re-centered operating points. Because a linearized master is structurally blind to voltage and reactive-power deficiencies, the master is guided by exact-AC feasibility cuts in the Benders tradition: a nonlinear subproblem computes the minimum load shedding of each stressed state, and its duals price every investment class simultaneously, including the reactive directions. The loop is a heuristic that terminates with a declared security certificate over a finite screening pool, and a margin election maximizes the certified traction-demand margin within a + 0.1% cost budget; every compared plan is judged by an independent, fixed-investment exact-AC validation over 400 days of jittered timetables with hard operating limits. On an IEEE 57-bus system coupled to six synthetic 25 kV corridors with calibrated train dynamics, the certified plan serves 398 of 400 unseen days of perturbed timetables, with shedding in only 2 of about 70,800 exact-AC states. Results show that coupling without exact-AC guidance is actively harmful, and that training on the nominal timetable alone leaves a small but real jitter tail.

Förderung

  • Ongoing Research Funding Program, King Saud University, Riyadh, Saudi Arabia

Zitieren

APA

Arif, A. (2026). AC-Guided Co-Expansion Planning of Power Grids Hosting High-Speed Railways. IEEE Access, 14, 168613-168632. https://doi.org/10.1109/access.2026.3748499

Vancouver

Arif A. AC-Guided Co-Expansion Planning of Power Grids Hosting High-Speed Railways. IEEE Access. 2026;14:168613-168632. doi:10.1109/access.2026.3748499

BibTeX
@article{Arif2026,
  author = {Arif, Anmar},
  title = {AC-Guided Co-Expansion Planning of Power Grids Hosting High-Speed Railways},
  journal = {IEEE Access},
  year = {2026},
  volume = {14},
  pages = {168613--168632},
  doi = {10.1109/access.2026.3748499}
}
Kostenlos starten →